Notable items
CE-2026-620 #
Temporary modification to parking and traffic regulations for Aéro Gatineau-Ottawa - September 18 to 20, 2026
The city is implementing temporary parking bans and traffic flow changes near the Gatineau airport to accommodate the Aéro Gatineau-Ottawa 2026 air show. These measures ensure public safety and traffic management during the event, with costs covered by the city's major events support program.
Read full translation

CONSIDERING THAT activities will take place at the airport on September 18, 19, and 20, 2026, as part of the Aéro Gatineau-Ottawa 2026 air show;

CONSIDERING THAT several civilian and military aircraft will be part of the programming for this edition of Aéro Gatineau-Ottawa 2026;

CONSIDERING THAT the modification to parking and traffic regulations is necessary to ensure the safety of participants and the fluidity of automobile traffic;

CONSIDERING THAT the Police Service will manage traffic control;

CONSIDERING THAT the costs related to road traffic modifications are covered in service according to the framework of the Programme de soutien aux grands événements via resolution number CM-2026-38 ratified on January 20, 2026:

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee authorize the temporary modification to parking and traffic regulations on certain streets located near the airport for the Aéro Gatineau-Ottawa 2026 event, namely:

Parking prohibited on September 18, 19, and 20, 2026, on both sides of the following streets:

  • chemin Industriel, between 244 and rue Louis-Bisson;
  • boulevard de l’Aéroport for its entire length.

Parking prohibited on September 18, 19, and 20, 2026, on one of the two sides of the following streets:

  • montée Dalton, between chemin Industriel and 443 montée Dalton, East/even side;
  • chemin Industriel, between 244 and montée Dalton, North/odd side.

Creation of a third central lane on September 19 and 20:

  • in exit 154 of Highway 50 eastbound to boulevard de l’Aéroport;
  • boulevard de l’Aéroport, between the Highway 50 westbound overpass and chemin Industriel.

A recognized company will install the signage according to the directives of the Mobility Department. All according to plan number G-15-027-01 and the following conditions:

  • respect the road signage standards of Quebec and the City of Gatineau regarding street closures;
  • ensure an emergency lane at all times during the event.

The organization commits to providing the Events Office of the Arts, Culture and Letters Department, two weeks before the event, a general civil liability insurance certificate of $3,000,000 and also commits to releasing the City of Gatineau from any liability for damages to others that may result from holding the event and to designate the City of Gatineau as an additional insured on their civil liability insurance policy. Adopted

CE-2026-621 #
Temporary modification to parking and traffic regulations for the Tour de Gatineau - September 16 and 17, 2026
The city is authorizing temporary street and parking closures to facilitate the Tour de Gatineau cycling event. These closures will affect various downtown streets on September 16 and 17, 2026, to ensure participant safety and traffic control.
Read full translation

CONSIDERING THAT the Tour de Gatineau will take place on September 16 and 17, 2026;

CONSIDERING THAT street closures and traffic control are essential elements for the safety of participants;

CONSIDERING THAT the Police Service will ensure traffic control for the entire duration of the event;

CONSIDERING THAT the costs related to road traffic control are provided for in the municipal budget, according to the terms in effect for the Programme de soutien aux grands événements, via resolution number CM-2026-341 adopted on May 12, 2026;

CONSIDERING THAT the temporary signage plan and the installation of the required temporary road signage are the responsibility of the organization according to the standards in effect:

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee authorize the closure of streets and parking lots (including parking meters) according to the following schedule:

The following streets must be closed to all traffic and all parking (except authorized vehicles) temporarily according to the following dates and times:

Date Hours Closed Streets and Parking
Tuesday, Sept 15, 2026 6 p.m. to 11 p.m. Rue Wellington – Between rue Laval and rue Saint-Jacques
Wednesday, Sept 16, 2026 7:30 a.m. to 4 p.m. Rue Wellington – Between rue Laval and rue Saint-Jacques
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Rue Saint-Jacques – Between rue Wellington and Promenade du Portage
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Promenade du Portage – Between rue Saint-Jacques and boulevard Alexandre-Tâché
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Boulevard Alexandre-Tâché – Between Promenade du Portage and rue Scott
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Rue Scott – Between boulevard Alexandre-Tâché and rue Graham
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Promenade Lac-des-fées – Between rue Scott and rue Gamelin
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Rue Gamelin – Between Promenade Lac-des-fées and Promenade Gatineau
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Promenade Gatineau – Between rue Gamelin and boulevard Alexandre-Tâché
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Boulevard Alexandre-Tâché – Between Promenade Gatineau and rue Eddy
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Rue Laurier – Between rue Eddy and rue Laval
Wednesday, Sept 16, 2026 9 a.m. to 3 p.m. Rue Laval – Between rue Laurier and rue Wellington
Thursday, Sept 17, 2026 7:30 a.m. to 8 p.m. Rue Wellington – Between rue Laval and rue Saint-Jacques
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Rue Saint-Jacques – Between rue Wellington and Promenade du Portage
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Promenade du Portage – Between rue Saint-Jacques and boulevard Alexandre-Tâché
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Boulevard Alexandre-Tâché – Between Promenade du Portage and rue Scott
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Rue Scott – Between boulevard Alexandre-Tâché and rue Graham
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Promenade Lac-des-fées – Between rue Scott and rue Gamelin
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Rue Gamelin – Between Promenade Lac-des-fées and Promenade Gatineau
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Promenade Gatineau – Between rue Gamelin and boulevard Alexandre-Tâché
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Boulevard Alexandre-Tâché – Between Promenade Gatineau and rue Eddy
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Rue Laurier – Between rue Eddy and rue Laval
Thursday, Sept 17, 2026 9 a.m. to 3 p.m. Rue Laval – Between rue Laurier and rue Wellington

The following parking areas must be closed temporarily according to the following dates and times:

Date Hours Closed Parking
Tuesday, Sept 15, 2026 00:00 to 24:00 Rue Wellington – Between rue Laval and rue Saint-Jacques
Tuesday, Sept 15, 2026 9 a.m. to 24:00 Rue Saint-Jacques – Between rue Wellington and Promenade du Portage
Tuesday, Sept 15, 2026 9 a.m. to 24:00 Rue Scott – Between boulevard Alexandre-Tâché and rue Graham
Wednesday, Sept 16, 2026 00:00 to 24:00 Rue Wellington – Between rue Laval and rue Saint-Jacques
Wednesday, Sept 16, 2026 00:00 to 24:00 Rue Saint-Jacques – Between rue Wellington and Promenade du Portage
Wednesday, Sept 16, 2026 00:00 to 24:00 Rue Scott – Between boulevard Alexandre-Tâché and rue Graham
Wednesday, Sept 16, 2026 00:00 to 24:00 Rue de l’Hôtel-de-Ville – Between rue Eddy and rue Laval
Thursday, Sept 17, 2026 00:00 to 24:00 Rue Wellington – Between rue Laval and rue Saint-Jacques
Thursday, Sept 17, 2026 00:00 to 3 p.m. Rue Saint-Jacques – Between rue Wellington and Promenade du Portage
Thursday, Sept 17, 2026 00:00 to 3 p.m. Rue Scott – Between boulevard Alexandre-Tâché and rue Graham
Thursday, Sept 17, 2026 00:00 to 24:00 Rue de l’Hôtel-de-Ville – Between rue Eddy and rue Laval

The following condition must be met:

  • obtain approval from the City of Gatineau for the temporary signage plan, respecting Quebec road signage standards and municipal requirements, no later than two weeks before the event. Adopted
CE-2026-625 #
Two-month unpaid suspension - Employee number 119150
The Executive Committee has authorized a two-month unpaid suspension for a city employee following an internal investigation into their conduct.
Read full translation

CONSIDERING the conclusions of the investigation conducted by representatives of the City of Gatineau;

CONSIDERING the nature of the breaches committed by employee number 119150;

CONSIDERING all the facts analyzed, internal equity, as well as the current state of jurisprudence in this matter;

CONSIDERING THAT the representatives of the Human Resources Department and the department concerned authorize the conclusions following the investigation:

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee authorize the imposition of a two-month unpaid suspension for employee number 119150. Adopted

CE-2026-626 #
Administrative termination of employment - Employee number 118120
The Executive Committee has authorized the administrative termination of a city employee who failed to return to work as required under the collective agreement.
Read full translation

CONSIDERING the signing of the collective agreement of the Syndicat des cols bleus on March 31, 2026;

CONSIDERING THAT the employee refused to return to work at the times determined by the employer;

CONSIDERING article 20.03 of the collective agreement;

CONSIDERING THAT it is appropriate to administratively terminate the employment relationship of the employee:

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee authorize the administrative termination of employment of employee number 118120. Adopted

STEVE MORAN, President, Executive Committee Me VÉRONIQUE DENIS, Clerk, Executive Committee

All items
CE-2026-619 #
Minutes of the Executive Committee meeting held on August 19, 2026
This is a routine procedural item to formally approve the minutes of the previous Executive Committee meeting held on August 19, 2026.
Read full translation

CONSIDERING THAT a copy of the minutes of the ordinary meeting of the Executive Committee of the City of Gatineau held on August 19, 2026, was provided to the members of the Executive Committee: PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee adopt the minutes as submitted. Adopted

CE-2026-622 #
Approval of the list of disbursements for the period of July 31 to August 6, 2026, in the amount of $14,179,951
This is a routine financial item to approve the city's expenditures for the week of July 31 to August 6, 2026, totaling $14,179,951.
Read full translation

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee approve the list and accept the filing of the list of disbursements for the period from July 31 to August 6, 2026, in the amount of $14,179,951. A treasurer's certificate was issued on August 27, 2026. Adopted

CE-2026-623 #
Approval of the list of disbursements for the period of August 7 to 13, 2026, in the amount of $11,052,043
This is a routine financial item to approve the city's expenditures for the week of August 7 to 13, 2026, totaling $11,052,043.
Read full translation

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee approve the list and accept the filing of the list of disbursements for the period from August 7 to 13, 2026, in the amount of $11,052,043. A treasurer's certificate was issued on August 27, 2026. Adopted

CE-2026-624 #
Extension of a temporary work overload assignment as a project coordinator for the Arts, Culture and Letters Department for a duration of four months
The committee approved a four-month extension for a temporary project coordinator position within the Arts, Culture and Letters Department. Because the total salary expenditure for this overload exceeds $250,000, it required formal Executive Committee approval.
Read full translation

CONSIDERING THAT under Règlement 816-2017 concerning the delegation of power from the Executive Committee to certain officials, including the power to authorize expenses and enter into contracts on behalf of the City of Gatineau, salary expenses associated with a work overload of more than $250,000 must be submitted to the Executive Committee;

CONSIDERING THAT the expense of $41,266.80 associated with the extension of this work overload means that the total amount is greater than the sum of $250,000;

CONSIDERING THAT the Human Resources Department was authorized to extend a temporary work overload assignment as a project coordinator for the Arts, Culture and Letters Department for a period of four months:

PROPOSED AND UNANIMOUSLY RESOLVED THAT this committee authorize the expense associated with the extension of this temporary work overload assignment as a project coordinator for the Arts, Culture and Letters Department for a duration of four months. The funds for this purpose will be taken from the Cultural Policy budget (69999-0191-10040-10040.01). A treasurer's certificate was issued on August 27, 2026. Adopted

governanceculture adopted Règlement 816-2017 human resourcesstaffingarts and culture $41,266.8